A can do piece of work in 10 days and B can do samework in 15 days how much time A and B together take to finish the work
Answers
Answered by
1
Step-by-step explanation:
A's 1day work =1/10
B's 1day work =1/15
(A+B)'s 1day work=1/10 +1/15 =3/30+2/30
. . . . . . . . . . . . . . . =5/30
. . . . . . . . . . . . . . . =1/6
1/6 work A and B can do in one day.
Hence, A and B together can do work in 1/6 days.