Math, asked by karsubhranshu459, 11 months ago

A can do piece of work in 24 days. If B is 60% more efficient than A then the number of days required by B to do the twice as large as the earlier work is?

Answers

Answered by shridharbelagavi900
2

Answer:

28.8 days

Step-by-step explanation:

Given, Time taken by A to do a work

= 24 days

B is 60% more efficient than B

Therefore, Time taken by A to do twice the work = 24 * 2 = 48 days

Hence, Time taken by B to do twice as large as earlier work = 60% of 48

= 60 * 48/100 = 144/5 = 28.8 days or

28 days 19 hours 12 minutes

Hence B will take 28.8 days to do the required work

HOPE IT HELPS, PLEASE MARK AS BRAINLIEST

Answered by shahdarshr121
1

Answer:

Step-by-step explanation:

Given, Time taken by A to do a work

= 24 days

B is 60% more efficient than B

Therefore, Time taken by A to do twice the work = 24 * 2 = 48 days

Hence, Time taken by B to do twice as large as earlier work = 60% of 48

= 60 * 48/100 = 144/5 = 28.8 days or

28 days 19 hours 12 minutes

Hence B will take 28.8 days to do the required work

Similar questions