Math, asked by ankitmishrabxr92, 2 days ago

a can do pieces of work in 60 day he worked for 15 days and then B alone finish the finish the remaining work in 30 day the two together can finish the work in how many days with statement​

Answers

Answered by singhamanpratap02
2

A can do a piece of work in 60 days.he works for 15 days and then b alone finishes the remaining work in 30 days. the two together can finish the work in

They toghether will take 24days to complete the work

Together they can finish the work in 24 days.

Given data :

A finishes in = 60 days

A Works for = 15 days

B finishes remaining work in = 30 days

Let,the total amount of work = 1

So, A finishes in 60 days = 1

A finishes in 1 day = 1/60

A finishes in 15 days = 15/60 = 1/4

Remaining work = 1-1/4 = 3/4

B finishes in 30 days = 3/4

B finishes in 1 day = 1/40

So,in 1 day

A+B finishes = 1/60 + 1/40 = (2+3)/120 = 5/120 = 1/24

So they finishes 1/24 work in = 1 day

They finishes 1 work in = 1 × 24/1 = 24 days (answer)