A can do s piece of work in 'x' days and B can do the same work in (x + 16) days. If both working together can do it in 15 days. Calculate 'x'
Answers
Answered by
0
Given A do a piece of work in x days and B do work in x+16 days
Then A one day work =
x
1
days
AND B one day work =
x+16
1
days
Then Both one day work =
x
1
+
x+16
1
=
x(x+16)
x+16+x
=
x
2
+16x
2x+16
So both do work in
2x+16
x
2
+16x
days
But both do work in 15 days
∴
2x+16
x
2
+16x
=15
⇒x
2
+16x=30x+240
⇒x
2
−14x−240=0
⇒x
2
−24x+10x−240=0
⇒x(x−24)+10(x−24)=0
⇒(x−24)(x+10)=0
Then x−24=0,x=24
And x+10=0,x=−10
But work done is not negative
Then work done =24 days