A can do some work 24 days b can do it 32 days and c can do it in 60 days. thay start working together. a left after 6 days and b left after working for 8days. how many more days are required to complete the whole work

Answers

Answered by BEJOICE
0
See the attachment for detail solution
Hope it will help you
Attachments:

BEJOICE: Sorry to say that I made some mistakes in the calculation
BEJOICE: Please repost the question, I will solve it correctly
BEJOICE: The correct answer is 22 days
BEJOICE: Pls inform after reposting the question