Math, asked by Palandr6865, 11 months ago

A can do some work in 24 days, b can do it in 32 days and c can do it in 60 days. They start working together. A left after 6 days and b left after working for 8 days. How many more days are required to complete the whole work?

Answers

Answered by santoshkandwal
2
Hope it helps you....
Attachments:
Answered by santy2
1

Answer:

16 1/4 days

Step-by-step explanation:

A can do the work in 24 days

B in 32 days

C in 60 days

Here is the fraction of work each can do in a single day:

A - 1/24 of the work

B - 1/32 of the work

C = 1/60 of the work

In a single day, together the three cover the following fraction of the work:

1/24 + 1/32 + 1/60  = (20 + 15 + 8)/ 480 = 43/480

Therefore, after 6 days when A leaves, the work done is:

43/480 × 6 = 43/80

The fraction of work left:

80/80 - 43/80 = 37/80

B and C then work 2 days together before B leaves on the 8th day. The work done on these 2 days is:

Fraction of B + Fraction of C done in a single day × 2

1/32 + 1/60 = (15+8)/480 = 23/480

There in the two days they cover ⇒ 23/480 × 2 = 23/240

The total work covered in the 8 days, therefore is:

43/80 + 23/120 = 35/48

So far 35/48 of the work is done, after 8 days C is alone. He is left with

48/48 - 35/48 = 13/48 of the work

C covers 1/60 of the work in a day, therefore how many days will he take to cover 13/48?

13/48 ÷ 1/60  = 13/48 ×60/1 = 13/4 × 5/1 = 65/4  

                                                                = 16 1/4

Therefore C requires 16 and a quarter more days to complete the work.


Similar questions