Math, asked by aish96, 11 months ago

A can do some work in 24 days, B can do
it in 32 days and C can do it in 60 days.
They start working together. A left after 6
days and B left after working for 8 days.
How many more days are required to
complete the whole work?

Answers

Answered by Anonymous
0

hiI mate here is ur solution,....

I hope it's helpful