A can do to 2/3 of a certain work in 16 days and B can do 1/4 of the same work in 3 days. In how many days
can both finish the work working together?
Answers
Answer:
8 days
Step-by-step explanation:
Let the total part of work be 1
2/3 part of work can be completed by A in 16 days
=> 1 part of work can be completed by A in 16÷ (2/3 )days
= 16*(3/2)= 24 days
Thus A alone can complete the work in 24 days
1/4 part of work can be completed by A in 3 days
=> 1 part of work can be completed by A in 3÷ (1/4 )days
= 3*(4/1)= 12 days
Thus B alone can complete the work in 12 days
A alone can do 1 part of work in 24 days
So, part of work A does in 1 day= 1/24
B alone can do 1 part of work in 12 days
So, part of work B does in 1 day= 1/12
So, part of work (A+B) can do in 1 day working together= (1/12)+(1/24)
= (3/24) = 1/8
So, 1/8 part of work is completed by (A+B) in 1 day
hence, 1 part of work can be completed by A+B in 1÷(1/8)= 8 days