A can do work 15 and B acn do work in 10 days .but B CAN DO WORK 8 DAYS AND REMIND WORK A can do work?
Answers
Answered by
0
Answer:
a can do a work in 234576
Answered by
1
Step-by-step explanation:
B 1 day work = 1/10
in 8 days B work = 8/10=4/5
remaining work =1-4/5=1/5
A in 1 day can work = 1/15
A can finish 1/5 work in 3 days