A can do work in 12 days B can do work in 15 days and C can do work in 20 days in what time can they complete the work together
Answers
Answer:
33 days
Step-by-step explanation:
- A can work 12 day
- B can work 15 days so 15- 12=3
- C can work 20 days so 20-12=8
- so 12+3+8=33 days
Answer:
If A can do a work in 12 days and B can do the work in 15 days and C can do it in 20 days, then A,B and C can together complete the work in 5 days
Step-by-step explanation:
Given
Number of days in which A can do the work = 12 days
Number of days in which B can do the work = 15 days
Number of days in which C can do the work = 20 days
Amount of work A can do in 1 day = of total work
Amount of work B can do in 1 day = of total work
Amount of work C can do in 1 day = of total work
Total amount of work A,B and C can do together in 1 day
Therefore amount of work A,B,and C can together do in a day = of total work
So, days for completing of work together = 1 day
days for completing 1 total work together = 1 day *5
= 5 days
Number of days required by A,B and C for completing the work together = 5 days