A can do work in 15 days and B in 20 days. Both together worked for 5 days and then A left the work. How long will B take to complete the remaining work??
answer fast pls...

Answers

Answered by pushpendra22
1
A's one day of work= 1/15

B's one day of work= 1/20

then work done by them together in one day = 1/15 + 1/20= 35/300

hence they together complete the work in 300/35 days

Now 5 days of their work with each other = 5x(1/15 + 1/20) = 1/3 + 1/4 = 7/12 days