Math, asked by ritishnan, 1 year ago

A can do work in 21 days, B can do same work in 23 days. How much work will they do together.

Answers

Answered by shivam7443
0
44/483 work done when both work together
Answered by TheLostMonk
1
correct question: A can do a work in 21 days and B can do the same work in 23 days . if they worked together then in how many days will the work be finished.

solution:
-------------

let total work done = 1

A's 1 day's work = 1 / 21 units

B's 1 day's work = 1/ 23 units

On working together:
------------------------------

(A + B)'s 1 day's work = (1/ 21) + ( 1/ 23)

= (23 + 21)/ 21 × 23 = 44/ 483

= 1/ 10.9 units

Answer:

the work will be finished in 10.9 days.