Math, asked by parasharlucky171, 2 months ago

A can finish 2/3 of work done by B in 1/4 of time taken by B. B can finish 4/3 of work done by C in 3/5 of time taken by C. Working together they can finish the work in 60 days. In how many days they will finish the work, working alone?​

Answers

Answered by Chandhini11
2

Answer:

Let x be the number of days that would take C to complete the job. In one day he does 1x of the job.

B can do 43 of any work done by C in 35 of the time that takes C to complete that much work (i.e. B is faster than C), therefore, in 3x5 days B does 43 jobs. Thus, B does the job in

3x5⋅34=9x20

days. In one day he does 209x of the job.

A can do 23 of any work done by B in 14 of the time that takes B to finish that much work (i.e. A is faster than B and the fastest of the three), hence, in

9x20⋅14=9x80

days A does 23 of the job. Consequently, A does the job in

9x80⋅32=27x160

days. In one day he does 16027x of the job.

We are now ready to calculate how much time it takes C to complete one job and thenceforth to compute the time needed by B and A to finish that much work by solving the following equation:

60⋅(16027x+209x+1x)=1

32009x+4003x+60x=1

3200+1200+540=9x

x=49409=20⋅2479

So C does the job in

49409

days (approximately 548.889 days).

B does the job in

9x20=920⋅49409=247

days.

A does the job in

27x160=27160⋅49409=3⋅2478

days (92.625 days).

We can verify this solution by adding their daily work outputs and checking whether that sum equals 160 :

83⋅247+1247+920⋅247=8⋅20+60+9⋅360⋅247=24760⋅247=160

hope this helps you

Similar questions