A can finish a job in 12 hours and B in 14 hours. A and B working alternatively, starting with A. If A earns Rs. 50 per hour, how
much does A earn through this job?
a Rs. 400
b. Rs. 250
C. Rs. 300
d. Rs. 350
Answers
Answered by
4
Answer:
The answer is R.s 350
,
Step-by-step explanation:
A's earns Rs. 350
Solution:
A's1 hour work =1/12
B's 1 hour work =1/14
A and b work together =1/12+1/14,
=>(7+6)'s 2 hours work =13/84,
A&b work alternatively l
So, (a+b)' s 2 hours =13/84
They work 6 pair of hours
Work =6*13/84=13/14
Remaining work =1-13/14=1/14
13th hour is A's turn
Total hour work by A=6+1 (to do 1/12)=7,A's earning amount = 50*7=R.s 350
Pls mark me as brainlist
Pls give thanks and mark me in brainlist if the answer is correct