Math, asked by minyubin777, 5 months ago

A can finish a job in 15 days, while B can do it in 10 days. How long will they take to do the job together?​

Answers

Answered by Deeptikashyap
5

Answer:

(A+B)'s 1 day's work =(

15

1

+

10

1

)=

6

1

Work done by A and B in 2 days =(

6

1

×2)=

3

1

Remaining work =(1−

3

1

)=

3

2

Now ,

15

1

work is done byA in 1 day,

3

2

work done by A in (15×

3

2

)=10 days

Answered by prakhar5344
4

Answer:

6 days

Step-by-step explanation:

1/15 + 1/10

= lcm 30

= 2/30+3/30

= 5/30 = 1/6

= 6 days