a can finish a job in 3 days whereas B finish it in 6 days the time taken to complete the up together in dash days
Answers
Answered by
9
A's 1day work=1/3
B's 1day work=1/6
A+B's together 1 day work= 1/3+1/6=3/6=1/2
so they both will take 1÷1/2 i.e. 2days
Attachments:
Answered by
22
The total number of days, A and B work together = 2 days
Step-by-step explanation:
Given,
A can finish a job = 3 days and
B can finish a job = 6 days
To find, the total number of days, A and B work together = ?
A's 1 day's job = and
B's 1 day's job =
∴ (A + B)'s 1 day's job =
=
=
=
∴ The total number of days, A and B work together = 2 days