a can finish a piece of work in 16days,and b in 20 days. they work together for 4days and after that, A leaves. how long will B take to complete the remaining work

Attachments:

Answers

Answered by shantanurauthan
18

                                                                   A             B              

                                                                  16            20

Total Work = LCM( 16 , 20) =                           80                      

                                                                  5              4

A do 5 units of work in 1 day and B do 4 units of work in 1 day

A + B do 5+4 = 9 units of work in 1 day

Total work  = 80 units

A and B work together for 4 days which means they both do 9 * 4 = 36 units of work

Now remaining work is  = 80 - 36 = 44 units

As B does 4 unit of work in 1 day

B can do 44 units of work in = 44/4 = 11 days


If you understood the answer mark it as brainliest

Happy Learning :)


Answered by alkajangid1973
1

Answer:

A can do a piece of work in 16 days and B can finish it in 20 days. They work together for 4

days and then A leaves. In how many days will B finish the remaining work?