A can finish a piece of work in 16days and b in 20days. They work together for 4days and after that a leaves.How long will b take to complete the remaining work?
Answers
Answered by
0
Work of A in one day = 1/16
Work of B in one day = 1/20
1/16 + 1/20
= 5/80 + 4/80 = 9/80
9/80 x 4 = 9/20
hence b has to complete 9/20 of the work
Work of B in one day = 1/20
1/16 + 1/20
= 5/80 + 4/80 = 9/80
9/80 x 4 = 9/20
hence b has to complete 9/20 of the work
Answered by
8
Here's your answer!!
_______________________________
A can finish a piece of work in 16 days.
One day work of A ,
B can finish a piece of work in 20 days.
One day work of B ,
Now,
(A+B)'s together one day work =
It is given that ,they worked for 4 days.
So,fraction of work completed =
Therefore,
Remain work =
Now,A has left and remain work has to be done by B.
So,time taken by B to complete remain work =
Hence,
B can complete the remain work alone in 11 days.
________________________________
Hope it helps you!! :)
_______________________________
A can finish a piece of work in 16 days.
One day work of A ,
B can finish a piece of work in 20 days.
One day work of B ,
Now,
(A+B)'s together one day work =
It is given that ,they worked for 4 days.
So,fraction of work completed =
Therefore,
Remain work =
Now,A has left and remain work has to be done by B.
So,time taken by B to complete remain work =
Hence,
B can complete the remain work alone in 11 days.
________________________________
Hope it helps you!! :)
Similar questions