A can finish a piece of work in 18 days and B can do the same work in half the time taken by A. Then working to their what part of the same work they can finish in a day?
Answers
Answered by
1
A can do the piece of work in 18 days.
One day work of A=1/18
B can do the work in half the time taken by A=2/18=9 days.
One day work of B =1/9
(A+B)'s one day work =
Hence,They can complete the work in 6 days
One day work of A=1/18
B can do the work in half the time taken by A=2/18=9 days.
One day work of B =1/9
(A+B)'s one day work =
Hence,They can complete the work in 6 days