a can finish a work in 12 days and B can do it in 15 days. after A had worked for 3 days, B also joined A to finish the remaning work. in who many days, the remaning work will be finished?
Answers
Answered by
0
The work completed by both in 2 days is
answer is 5 days sorry
fonikum98gmailcom:
no answer is 5 days
Answered by
1
hope you got it if any doubt ask me tq