Math, asked by ranjan2343, 1 year ago

A can finish a work in 12 days and B can do it in 15 days,after A had worked for 3 days, B also joined A to finished the remaining work in how many days the remaining work will be finished.

Answers

Answered by wifilethbridge
98

Answer:

5 days

Step-by-step explanation:

A can do work in days = 12

A's 1 day work = \frac{1}{12}

A's 3 days work = \frac{3}{12} =\frac{1}{4}

Remaining work = 1-\frac{1}{4} = \frac{3}{4}

B can do work in days = 15

B's 1 day work = \frac{1}{15}

(A+B)'s 1 day work = \frac{1}{15}+\frac{1}{12}

(A+B)'s 1 day work = \frac{1}{15}+\frac{1}{12}=\frac{3}{20}

A+B can do \frac{3}{20} work in days = 1

A+B can do  work in days = \frac{20}{3}

A+B can do\frac{3}{4}  work in days = \frac{20}{3} \times \frac{3}{4}=5

Hence Remaining work can be done in 5 days

Answered by redphoenix90
3

Step-by-step explanation:

5 days

Step-by-step explanation:

A can do work in days = 12

A's 1 day work = \frac{1}{12}

12

1

A's 3 days work = \frac{3}{12} =\frac{1}{4}

12

3

=

4

1

Remaining work = 1-\frac{1}{4} = \frac{3}{4}1−

4

1

=

4

3

B can do work in days = 15

B's 1 day work = \frac{1}{15}

15

1

(A+B)'s 1 day work = \frac{1}{15}+\frac{1}{12}

15

1

+

12

1

(A+B)'s 1 day work = \frac{1}{15}+\frac{1}{12}=\frac{3}{20}

15

1

+

12

1

=

20

3

A+B can do \frac{3}{20}

20

3

work in days = 1

A+B can do work in days = \frac{20}{3}

3

20

A+B can do\frac{3}{4}

4

3

work in days = \frac{20}{3} \times \frac{3}{4}=5

3

20

×

4

3

=5

Hence Remaining work can be done in 5 days

Similar questions