Math, asked by kirtan6354, 7 months ago

A can finish a work in 12 days B can finish the same work in 18 days and C in 24 days. C alone started the work after 2 days B joined C, after 2 day A also joined. In how many days the work will get finish? ​

Answers

Answered by snehaj5002
9

Answer:

FOLLOWING IS THE ANSWER

Step-by-step explanation:

A can do 1/12 the work in one day.

B can do 1/24 the work in one day.

If they both work for a day they will complete,

1/12 + 1/24 = 3/24 =1/8 work in one day.

1/8th work × 8 days of this work gives one unit of work.

Always try to think of how much each can accomplish in one day and then add every individuals work for one day and then the fraction of work thats accomplished in one day × number of days to make that fraction to 1 gives the answer.

Assumption: A and B work their maximum potential on each day.

HOPE IT WILL BE HELPFUL

PLEASE MARK AS BRAINLIEST