A can finish a work in 15 days and B can finish it in 60 days. B worked for 10 days and left the on many days A alone can finish the remaining work?
Answers
Answered by
1
Answer:
B worked for 10 days. So, remaining 5 days work is pending. This is 5/15 = 1/3rd of work.
a can finish the work in 18 days. So, 1/3rd of work can be done in 18 × 1/3 = 6 days.