Math, asked by samreen37, 2 months ago

a can finish a work in 16 days and B can do the same work in 20 days they both work together for 8 days and then a letter leaves the work and goes away how many days will be take to finish the work

Answers

Answered by prasanthikuchipudi
1

Answer:

18 days

Step-by-step explanation:

Given,

a can finish a work in 16 days

A=1/16 days

B can do the same work in 20 days

B=1/20

LCM of 16,20 is 80

they both work together for 8 days

A+B=8/80 days

A+B=1/10 days worked

remaining work is 1-1/0=9/10

after 8 days A leaves so B has to do remaining work in 20 days

9/10*20=18 days