A can finish a work in 16 days and B
can finish the same work in 20 days.
After A had worked for 4 days, B also
joined with A to finish the remaining
work. In how many days will the
remaining work be finished?
Answers
Answered by
2
6.66 days
Fraction of work done by A in 1day = 1/16
Fraction of work done by A in 4 days = 4/16 = 1/4
Fraction of work done by B in 1 day = 1/20
Fraction of work done by A & B in 1 day = ( 1/16) +(1/20 ) = (20+16)/320
= 36 /320 = 9/80
Work remaining = 1- (1/4 ) = 3/4
No.of days required to complete the work by A & B working together
= (3/4) /(9/80) = ( 3x80)/(4x9) = 240/36 = 60/9=6.66
A & B would require 6.66 more days to complete the remaining work .