A can finish a work in 16 days and B can finish the same work in 20 days. After A had worked for 4 days, B also joined with A to finish the remaining work. In how many days will the remaining work be finished? A. 8 1/9 days B. 6 ⅔ days C. 8 8/9 days D. 6 ⅓ day​

Answers

Answered by anajanakanwar
0

Answer:

B

81/9days

Step-by-step explanation:

I I hope you like the answer