Math, asked by talukdarshubham07, 29 days ago

A can finish a work in 20 days, and B take 25 days to finish the same work both of them started together but after 4 days A left the work Then now in how many days will B finish the rest of the work

Answers

Answered by singhakriti866
2

Answer:

As A and B do same work

LCM (20,25)=100

Let say A and B do 100 work

Per day work of A=100/20=5

Per day work of B=100/25=4

Per day work if A and B both work together=5+4=9

Both together worked for 5 days.

Therefore work completed in 5 days=5×9=45

Now work which is left =100–45=55

As A left the work after 5 days ,B alone will work to complete 55 work

Per day work of B ×days = 55

days =55/4

days=13 3/4

Therefore total work will be completed by

5+13 3/4=18 and 3/4 days

Answer is 18 3/4

Hope this helps you & pls mark me brainliest.