Math, asked by sujalxdx, 1 year ago

A can finish a work in 20 days, while B can finish it in 12 days. A started the work alone and after 4 days B joined him and they work together till the work was completed. For how long did they work together?

Answers

Answered by tanmaybhere100
1

Answer:


Step-by-step explanation:

Work by A in 1 day = 1/20

Work by B in 1 day = 1/12

Together they work = (1/20)+(1/12) = (3 + 5)/60 = 8/60 = 2/15

Total time taken by them = 7.5 days

But here A work 5 days alone.

Work by A in 5 days = (3/60)×5 = 15/60

Let x be the number of days they work after.

After that they work together,

(15 + × (3+8))/60 = 1

8x = 60 - 15

x = 45/8

x = 5(5/8) days

Total time taken = 5 + 5 (5/8) = 10 (5/8)days


sujalxdx: wrong
sujalxdx: answer is 6 days
sujalxdx: plz reply