Math, asked by jits73patel, 1 year ago

A can finish the job in 18 days. B can do the the jon in 15 days. B worked for 10 days left yhe job in how many days can A alone finish the remaning work?

Answers

Answered by fruitwargi
4
here is your answer dear...

In 15 days B completes the work
In 10 days B completes 1×10/15 =2/3 parts of total work. Remaining work is 1–2/3=1/3 of the total work done by A.
A completes the work in 18 days
A performs 1/3 of the work in 18×1/3 = 6 days

hope I helps you dear..
❤❤❤⭐⭐⭐⭐❤❤❤
Attachments:
Answered by mannatmarya
3

Hello

here is your answer dear...

In 15 days B completes the work

In 10 days B completes 1×10/15 =2/3 parts of total work. Remaining work is 1–2/3=1/3 of the total work done by A.

A completes the work in 18 days

A performs 1/3 of the work in 18×1/3 = 6 days

hope I helps you dear

Plz mark me as brain liest

Plz mark me as brain liest

Plz


mannatmarya: Plz mark me as brain liest
mannatmarya: Plz