A can finish the job in 25 days and B can finish it in 30 days. After working together for 4 days, A leaves the job. In what time will B finish the remaining job, working alone?
GIVE ANSWER WITH STEPS
Answers
Answered by
0
Answer:
and B do 5[(1/25)+(1/30)] = 5*(30+25)/(25*30) = (5*55/750) = (1/2.7)th of the work in 5 days. After 5 days when A leaves the work, the work remaining is (1.7/2.7)th of the work.
The remaining work can be done by B alone in (1.7/2.7)/(1/30)
= 1.7*30/2.7
= 18.9 days.
Answered by
3
A's WORK=
B's WORK=
A's AND B's TOGETHER 1 DAY's WORK
=+==
NOW THE REMANING WORK DONE BY B
LET B TAKES X DAY TO COMPLETE THE WORK
X=3
HENCE B WILL TAKE 3 DAYS TO COMPLETE WORK
Similar questions
Math,
15 days ago
Science,
30 days ago
Science,
30 days ago
Social Sciences,
8 months ago
Geography,
8 months ago