A can finish the work in 15 days, b in 18 days and c in 20 days. B and c starts the work together and are found to leave after 4 days. Then what is the time taken to finish the remaining work.

Answers

Answered by rahul20vaishnav
0

Answer:

Step-by-step explanation:

Let the total work is 180 unit

Work done by A in one day = 12 unit

Work done by b in one day = 10 unit

Work done by sea in one day = 9 unit

B+C= 19 unit for four days 76 unit by both

Total 180

Remaining work 180-76=104 unit

time taken by a = 104/12 days