A can finish the work in 18 days and B can do the same in 15 days . B alone worked for 10 days and left the job. If A alone has to finish the remaining work the number ofdays it takes is
Answers
Answered by
8
We will use the LCM technique to solve this.
A takes 18 days to complete the task whereas B takes 15 days to complete.
Let the TOTAL WORK = 90 Units
So, A does 5 Units/day
B does 6 Units/day
B worked for 10 days and left the job. So, work done by B = 60 Units
Remaining Work = 30 Units.
Thus, A will take = 305305 = 6 Days (Answer)