A can finish the work in 18 days and B can finish the work in 27 days . A work for 10 days and left the job . In how many days alone will B finish the remaining work
Answers
Answered by
1
Answer:
Lcm of 18,27 is 54
Total work is 54
A=54/18=3
B=54/27=2
A*10+B*X=54
3*10+2*X=54
2X=24
X=12
B finish the remaining work in 12 days