a can fo a piece of work in 10 days and b in 20 days. they begin together but a leaves 2 days before the completion of the work. in how many days will the whole work be completed
Answers
Answered by
5
Given:-
- A can do a piece of work in 10days.
- B can do it in 20 days.
- They begin together but A leaves 2 days before the completion of the work.
To find:-
- No.of.days in which the whole work will be completed.
Solution:-
Let us consider that the work is done in 'x' days
Then,
In 1 day:
Work of A = 1/10
Work of B = 1/20
Given that A leaves 2 days before,
A works for (x-2) &
B works for x days
According to question,
Hence,
The work will be completed in 8 days.