A can have a piece of work in 8 days, B can work 3 times faster than A. C can do work 5 time faster than A .How many days they will do work together.
Answers
Answered by
0
Answer:
Let efficiency of A - 1 units
so, efficiency of B - 3 units
efficiency of c - 5 units
If A can complete a piece of work in 8 days so total work will br 8 ×1 = 8 units.
And , Total efficiency of A+B+C = 9 units..
If all three together do the work the will be completed in = 8/9 Days...