A can lay railway track between two given stations in 16 days and B can do the same job in 12 days with help of C they did the job in 4 days. only C alone can do the job in how many days?
Answers
Answered by
17
Answer is in the attachment.
Mark me as a Brainliest.
Mark me as a Brainliest.
Attachments:
liki66:
thanks
Answered by
2
Answer:
Step-by-step explanation: