A can lay railway track between two stations in 16 days and B can do same work in 12 days. With the help of C, they completed the work in 4 days only. How much time C alone will take to complete the work​

Answers

Answered by kblavanya97
0

Answer:

Step-by-step explanation:

a = 1/16

b = 1/12

a +b+ c =1/4

c = a+b+ c - (a +b)

= 1/4 - (1/16+1/12)

=1/4 - ( 7/48)

= 12-7/48

=5/48

=48/5 = 9 3/5 days