a canal is dug by 32 men in 15 days . if there are only 12 men how long will they take to complete the work
please explain the answer
Answers
Answered by
20
Answer:
Step-by-step explanation:
This is a question of inverse proportion.
If there are more men they will complete the work in a lesser number of days but if there are less men they will complete the work in more days. Therefore:-
15/12 × 32
= 40 days
12 men will take 40 days to complete the work.
Answered by
8
Hope my answer will surely helps u...
=> 15/12 × 32
=> 40 days
Similar questions
Hindi,
5 months ago
Science,
5 months ago
Computer Science,
10 months ago
English,
1 year ago
Math,
1 year ago