Math, asked by sharkrated346, 10 months ago

A certain job was assigned to a group of men to be completed in 20 days. But 12 men did not turn up for the job and the
remaining men completed the job in 32 days. What was the original number of men in the group?

options
A 32
B 34
C 36
D 40​

Answers

Answered by dpray1987
0

Answer:

32

Step-by-step explanation:

Is a always correct person then i am sure but i dont do on the question on rough