Math, asked by asimirza595, 1 year ago

A certain number man can finish a piece of work in 50 days. If there are 7 more men, the work can be completed 10 days earlier. How many men were originally there?

Answers

Answered by Monu631
175
Let the no. of men originally be x.
Now, x men can finish work in 50 days.
So, x+7 men will do it in 50 *x /(x+7).
As per the question,
50x /(x+7) = 40
50x = 40x +280
10x = 280
x = 28.
So, No. of men originally there= 28.

◆Hope you will find it helpful◆
●●Mark it as brainliest●●
Answered by Hansika4871
2

Given:

A certain number of men can finish the work in 50 days. If 7 more men are added to the team, the work can be completed 10 days earlier.

To Find:

The number of people who initially worked is?

Solution:

1. A certain number of men can finish the work in 50 days.

2. Let the initial number of men be assumed as x,

=> x men can finish the work in 50 days.

3. If there are 7 more men, the work can be completed 10 days earlier,

=> x + 7 men can finish the work 10 days earlier,

=> x + 7 men can finish the work in 40 days.

4. The initial number of men can be calculated as follows,

=> If it takes 50 days to complete a certain work in x days,

=> The time taken by x + 7 people to finish the same job is (50)*(x)/(x+7),

=> Time taken by x + 7 people to finish the job  = 40 days,

=> (50x)/(x+7) = 40,

=> 50x = 40x + 280, ( solve for the value of x ),

=> 50x - 40x = 280,

=> 10x = 280,

=> x = 280/10,

=> x = 28.

5. Hence, Initial number of men = 28.

Therefore, the total number of men originally are 28.

Similar questions