A certain number of men can complete a piece of work in 160 days. If there are 30 men less, it will take 20 days more for the work to be completed. How many men were there originally?
Answers
Answered by
1
Answer:
your answer is 120 men.
Step-by-step explanation:
No. of days=160
no.of men=x
men left=x-30
days increased by=160+20=180
no. of days=160 180
no. of men=x x-30
=160/180=x-30/x
=160x =180x-2400
=2400= 180x - 160x
=2400= 20x
x=120 men
hope it helps.....
please mark as the brainliest!!