A certain number of men can complete a piece of work in 90 days if however there were 15 men less it would take 10 days more for the same work be completed how many men were there originally?
Answers
Answered by
2
Step-by-step explanation:
Let there be p men. They complete a work in 90 days. Hence the work requires the contribution of 90p men-days.
If the number of men was 8 less, the work would take 10 days more, or, (90+10)(p-8) men-days.
Equating the two we get
90p = (90+10)(p-8) =100(p -8) = 100p - 800, or
100p - 90p = 800, or
10p = 800, or
p = 80.
So there were 80 men in the originally.
Check: The work is done in 80*90 = 7200 men-days. With 72 men it would take 7200 men-days/72 men = 100 days. Correct.
Answered by
2
Let X number of men were originally working.
Now coming to the question, 90X = 1 work
(X-8)*(90+10) = 1 work.
So, 90X = (X-8)100
100X -90X = 800
10X = 800
So , X = 80 men were originally working there.
HOPE IT WILL HELP YOU BRO
Similar questions