A certain number of men can do a work in 60 days. If there were 8 men more
it could be finished in 10 days less. How many men are there?
Answers
Answered by
2
Step-by-step explanation:
Let the number of men be 'x'
x men will do a work in 60 days
1 man will do the work in 60x days
x+8 men will do a work in (60-10) = 50 days
1 man will complete the work in 50x + 400 days
ACCORDING TO QUESTION :
60x = 50x + 400
or, 60x - 50x = 400
or, 10x = 400
or, x = 400/10
or, x = 40
Therefore there were 40 men in the beginning