a certain number of men can finish a piece of work in 50 days . if there are 7 more men, the can be completed 10 days earlier . how many men were originallythere?
Answers
Answered by
6
Let the no of original men be 'x'
Work complete in 50 days.
If x + 7 then work completed in 40 days.
Then, x by 50 = (x+7) by 40.
Cross multiplication.
40 x = ( x + 7 )* 50
40 x = 50x + 350.
2x = 400 by 40
x = 5 men.
sankarkundu12:
sorry but answer doesn't match