a certain number of men complete a piece of work in 20 days. if 2 men wer
e excluded it would take 4 days more to complete. how many days men originally work here
Answers
SOLUTION
GIVEN
- A certain number of men complete a piece of work in 20 days
- If 2 men were excluded it would take 4 days more to complete.
TO DETERMINE
The number of men originally work here
EVALUATION
Let the number of men originally work here = x
Then x men complete a piece of work in 20 days
Now it is given that if 2 men were excluded it would take 4 days more to complete.
So ( x - 2) complete the same work in ( 20 + 4) = 24 days
Here the number of men and the number of days are in inverse proportion
Hence
Hence the number of men originally work here = 12
FINAL ANSWER
The number of men originally work here = 12
━━━━━━━━━━━━━━━━
Learn more from Brainly :-
1. 96 men are engaged for a project of constructing a railway track of length 18 km in four weeks.after one week it was
https://brainly.in/question/26617473
2. Antony gave 3/5 of his land to his son John. John gave 2/3 of his land to his dughter Mary. How much of Antony's land
https://brainly.in/question/29499452