Math, asked by mrani00001, 10 months ago

A certain number of people were supposed to complete a work in 24 days. The work , however,took,32 days since 9people were absent through out. how many people were supposed to be working originally​

Answers

Answered by amitnrw
1

Given : A certain number of people were supposed to complete a work in 24 days.

The work , however,took,32 days since 9people were absent through out.

To Find : how many people were supposed to be working originally​

Solution:

People supposed to be working originally​ = P

supposed to complete a work in 24 days.

Hence total work = 24P

9people were absent

Hence people worked = P - 9

Work completed  in 32 days

Hence total work =  32(P - 9)

Equate total work

32(P - 9) =  24P

=> 32P  - 32 * 9  = 24 P

=> 8P   = 32 * 9

=> P = 4 * 9

=> P = 36

36  people were supposed to be working originally​

Learn More:

20 men can complete a piece of work in 15 days. One man starts the ...

brainly.in/question/9066294

A work is completed such that on the nth day from the start n men ...

brainly.in/question/11508647

Similar questions