Math, asked by shahisugam123, 1 year ago

A certain number of workers are employed to construct a road in 24 days working 9 hours a day. How many hours a day should they work you the construction 6 days earlier?

Answers

Answered by sunrose48
11
Number of hours to construct a road in 24 days = 9 hours

Number of hours to construct a road in 1 day = 9 × 24 =216

Number of hours to construct a road in 6 days earlier (24 - 6= 18) =216 ÷ 18 = 12

So people have to work for 12 hours to complete the construction 6 days earlier
Similar questions