A certain piece of work was to be completed by 4 men and 8 women. They complete (2/5th) of the work in 4 days. 3 men joined them and together they completed the remaining work in 2 days less than what the initial team would have taken. If the work was to be completed by 20 men, how many days would they take?
Answers
Answer:
certain piece of work was to be completed by 4 men and 8 women. They complete (2/5th) of the work in 4 days. 3 men joined them and together they completed the remaining work in 2 days less than what the initial team would have taken.
If the work was to be completed by 20 men, then they would have taken 3 days.
Step-by-step explanation:
Step 1:
It is given that,
The amount of work done by 4 men & 8 women in 4 days = th
So, the amount of work done by 4 men & 8 women in 1 day will be = = th of work
∴ 4 men + 8 women can complete the work in 10 days ....... (i)
and
Also, The remaining work i.e., 3/5th of work is done by 4 men + 8 women in 10 - 4 = 6 days
Step 2:
Now, 3 more men joined the group of (4 men + 8 women) and because of which the remaining work i.e., (1 - 2/5 = 3/5th work) is done in 2 days less than what the initial team would have taken i.e., (6 - 2) = 4 days.
New team becomes = 4 men + 8 women + 3 men = 7 men + 8 women
By using the Man-Days formula, we get
[(4men+8women) * 4] / (2/5) = [(7men+8women) * 4] / (3/5)
⇒ [(4men+8women) * 2] = [(7men+8women) * 4] /3
⇒ [(4men+8women) * 6] = [(7men+8women) * 4]
⇒ 24 men + 48 women = 28 men + 32 women
⇒ 16 women = 4 men
⇒ 1 men = 4 women ........ (ii)
Therefore, from eq. (ii), we can write
4 men + 8 women as ⇒ 4 men + (1/4 * 8) men = 4 men + 2 men = 6 men can complete the work in 10 days ..... [as written in eq. (i)]
Finally, by using the Man-Days formula again, we get
6 men * 10 days = 20 men * (no. of days)
⇒ No. of days = 3 days
Thus, 20 men would have taken 3 days to complete the work.
--------------------------------------------------------------------------------------------------
Also View:
4 Men and 6 Boys can finish a piece of work in 5 Days , While 3 Men and 4 Boys can Finish it in 7 days . Find the time taken by 1 man alone or that by 1 boy alone ?
https://brainly.in/question/4117743
2 person can complete piece of work in 9 days. how many more persons are needed to complete double work in 12 days?
https://brainly.in/question/6624052
540 man days of work can be completed by a certain number of men in some days. If the numbers of people (men) are increased by 27. then the number of day required to complete the same work is decreased by 15. The number of days are required to complete the three times work (than the previous/actual work) 67 27 men?
https://brainly.in/question/12888958