A certain task can be completed in 6 days by 18 men. It is expected to complete another task which is twice the size of the initial task in 9 days. Find how many men are required to complete the second task in 9 days
Answers
Answered by
0
Step-by-step explanation:
task days men
1 6 18
2 9 ?
=(2/1) *(6/9) *18
=(2*6*18)/(1*9)
=24 men
Answered by
0
Answer:
24 days
Step-by-step explanation:
formula is
men×time/work=men×time/work
let ,
'm' is the men required in second case
'w' is the task in first case then
task in second case =2w
by formula
18×6/w=m×9/2w
after solving it
m= 24