A certain work can be done in a certain time by 36 men but had there had been.9 more men it could have been done in 5 days less in how many days can 20 men do the same work
Answers
Answered by
11
suppose total number of men = x
x men can work a job in 60 days
x men can work 1/60 job in 1 day
1 man can work 1/60x in 1 day..........................1
x+8 can do the same job in 50 days
similarly,
1 man can do 1/50(x+8) job in 1 day ..............2
from 1 and 2, 1/60x = 1/50(x+8)
solving the equation, x = 40 men.
x men can work a job in 60 days
x men can work 1/60 job in 1 day
1 man can work 1/60x in 1 day..........................1
x+8 can do the same job in 50 days
similarly,
1 man can do 1/50(x+8) job in 1 day ..............2
from 1 and 2, 1/60x = 1/50(x+8)
solving the equation, x = 40 men.
Answered by
1
Answer:
45
Step-by-step explanation:
Let unknown day be x
work done(W) by 36M= 1/x
W by 1 M =1/36x ---------(1)
9 more men =36 +9=45
similarly,
W by 45M = 1/(x-5)
W by 1M = 1/45×(x-5) --------(2)
(1)=(2)
1/36x=1/(45x-225)
x=9/225
from (1)
20M= 20/36x=5/9x
simplifying x
20M= 1/45
so 45 days